Campaign Planning and Results⚓︎

Use this page to size an acceptance campaign: how long each domain takes, what it needs in devices, radios and sites, and in which order to run it. Durations are planning figures for one engineer executing the published procedure once, excluding environment preparation.

Effort and resources by domain⚓︎

Domain Tests Planned duration UEs (max) Radios (max) Sites (max) Needs xRouter Needs simulator
Installation checks 5 3 h 35 min 1 1 1 No No
Session lifecycle 13 7 h 10 min 3 1 1 No No
Provisioning 11 4 h 15 min 2 1 1 No No
Policy and traffic 8 3 h 40 min 2 1 1 Yes No
Public network access 3 1 h 45 min 1 0 1 Yes No
Mobility and access transitions 7 7 h 30 min 1 2 2 Yes No
Security and isolation 12 5 h 45 min 2 1 2 No Yes
Messaging (SMS) 6 2 h 30 min 2 0 1 Yes No
Session records and usage 6 2 h 40 min 1 1 2 Yes No
Resilience and high availability 16 13 h 15 min 3 1 2 Yes No
Capacity and stability 4 29 h 45 min rated tier 1 1 No Yes
Operations and maintenance 6 4 h 40 min 3 1 1 No No
Total 97 86 h 30 min

Suggested sequence⚓︎

  1. Installation and Upgrade Verification (19 tests, about 7 h 10 min). Run first; it proves the deployment is ready for the rest of the campaign.
  2. Installation checks (5 tests, about 3 h 35 min).
  3. Session lifecycle (13 tests, about 7 h 10 min).
  4. Provisioning (11 tests, about 4 h 15 min).
  5. Policy and traffic (8 tests, about 3 h 40 min).
  6. Public network access (3 tests, about 1 h 45 min).
  7. Mobility and access transitions (7 tests, about 7 h 30 min).
  8. Security and isolation (12 tests, about 5 h 45 min).
  9. Messaging (SMS) (6 tests, about 2 h 30 min).
  10. Session records and usage (6 tests, about 2 h 40 min).
  11. Resilience and high availability (16 tests, about 13 h 15 min).
  12. Capacity and stability (4 tests, about 29 h 45 min).
  13. Operations and maintenance (6 tests, about 4 h 40 min).

Recording results⚓︎

Download results-template.csv: one row per published test, with columns for the result (Pass, Fail, Deviation, Not run), the tester, the date, the evidence reference and the deviation record. Expeto reviews the completed sheet with the operator before sign-off.